Gwynedd Mercy Academy High School Renovations
Project summary
New academic wing HVAC systems and library renovation
- Managed, coordinated, and supervised the installation of new air conditioning systems throughout the school’s academic wing.
- Received RFPs from pre-qualified engineering firms, awarded design work, and completed contracts.
- Solicited firm price proposals from an invited list of pre-approved mechanical contractors.
- Renovated the existing library into a state-of-the-art learning commons.
- Worked with architectural design firm to develop construction plans and specifications.
- Worked with the school’s facilities committee and architect to collect firm price bids.
- Managed communications between architects, contractors, school administration, and facilities department.
- Conducted pre-planning and formulated pre-construction schedule and techniques.
- Reviewed and approved all change orders.
- Both projects were completed on-time within a tight timeframe during the school’s twelve week summer recess.
Budget
$1.18M
Timeframe
May 2014 - August 2015
Location
Gwynedd Valley, PA